Over Budget and Late in Australia's Biggest Defence Projects

January 05, 2020 Add Comment
06 Januari 2020


Three AWD are $1.9bn over budget and more than three years late (photo : Clyde Dickens)

$10bn blowout to fighter jets, ships

Australia’s biggest defence projects are running $10.2 billion over-budget and an average of 27 months late, setting back the deployment of new capabilities amid growing strategic risks.

While China rolls out new military hardware, the navy’s three Air Warfare Destroyers are $1.9bn over budget and more than three years late, while the RAAF’s P-8A Poseidon maritime patrol aircraft are nearly two years behind schedule and almost $1.8bn over budget.

The report reveals the cost of the nation’s Joint Strike Fighters have blown out by $3.2 billion since they received “second pass” approval by cabinet, and the RAAF’s EA-18G Growler electronic attack aircraft are $868m over budget.


The RAAF’s EA-18G Growler electronic attack aircraft are $868m over budget (photo : PaulC7001)

The troubled multi-role helicopter project is running $250m over budget and more than seven years’ late for final operational capability, while the acquisition of 2,707 medium and heavy trucks are 11 months behind schedule and $115m over-budget.

“Delivering major projects on schedule continues to present challenges for Defence, affecting when the capability is made available for operational release and deployment by the Australian Defence Force, as well as the cost of delivery,” the Auditor-General said.

The 2018-19 report reveals that since the projects were first approved, their combined budgets had increased by more than $24 billion, however that included an additional 58 JSF’s and 34 MRH90 helicopters.


RAAF’s P-8A Poseidon maritime patrol aircraft are nearly two years behind schedule and almost $1.8bn over budget (photo : Aus DoD)

Since the scope of the projects was finalised, their total cost increased by $10.2bn, including $2.8bn for inflation and $4.4bn as a result of foreign exchange movements.

Opposition defence industry spokesman Pat Conroy claimed Coalition “mismanagement” of the defence portfolio was behind the blowouts and delays.

“This is the direct responsibility of Defence Minister Linda Reynolds and Defence Industry Minister Melissa Price,” Mr Conroy said.

The cost of the nation’s Joint Strike Fighters have blown out by $3.2 billion (photo : Michael Clarke)

He said the Ministers needed to “do their jobs and bring in these important Defence projects on time, on budget and on spec”.

Centre Alliance Senator Rex Patrick blasted Defence over the delays, claiming the department was “incompetent in its original assessments” of projects, requiring ministerial interventions.

“It’s not just the schedule and cost blowouts in the original project that needs to be considered,” he said.


The MRH-90 multi-role helicopter project is running $250m over budget and more than seven years’ late for final operational capability (photo : Contact)

“There’s the cost to the men and women in the Defence Force who are forced to carry out their tasks with obsolete equipment. There’s also the financial cost of Defence of keeping old and tired equipment running.”

Australian Strategic Policy Institute analyst Marcus Hellyer said there was “certainly room for improvement on schedule”.

However, in many cases, he said hardware was already in use by defence before the final capability was delivered.


2.707 units of medium and heavy trucks are 11 months behind schedule and $115m over-budget (photo : Rheinmetall)

“Major projects are complex. They do tend to run late,” Mr Hellyer said.

“On the other hand, when you see projects running seven or eight years late, it’s generally not the case that defence hasn’t gotten anything.

“Often it’s the case that it is still trying to deliver the last five or ten per cent of capability.”

Raytheon has Contracted AIM-120 AMRAAM Delivery to the US and 22 Countries, Including Indonesia

December 29, 2019 Add Comment
30 Desember 2019


AIM-120C7 AMRAAM (photo : almrsal)

Raytheon Missile Systems Co., Tucson, Arizona, has been awarded a $768,283,907 non-competitive fixed-price incentive (firm) contract for Advanced Medium Range Air-to-Air Missile (AMRAAM) Production Lot 33. This contract provides for the production of the AMRAAM missiles, captive air training missiles, guidance sections, AMRAAM telemetry system, spares and other production engineering support hardware.  

Work will be performed in Tucson, Arizona, with an expected completion date of Feb. 28, 2023. This contract involves unclassified foreign military sales to Australia, Belgium, Canada, Denmark, Indonesia, Japan, Kuwait, Morocco, Netherlands, Norway, Oman, Poland, Qatar, Romania, Saudi Arabia, Singapore, Slovakia, South Korea, Spain, Thailand, Turkey and United Kingdom, which accounts for 47% of the contract value. 

Fiscal 2018 Air Force and Navy procurement funds in the amount of $21,606,031; fiscal 2019 Air Force and Navy procurement funds in the amount of $356,753,259; fiscal 2020 Navy procurement funds in the amount of $4,212,839; fiscal 2019 Air Force research and development funds in the amount of $7,343,150; fiscal 2020 Air Force and Navy research and development funds in the amount of $10,295,601; fiscal 2020 Air Force operation and maintenance funds in the amount of $1,404,956; and foreign military sales funds in the amount of $366,668,071 are being obligated at the time of award. The Air Force Life Cycle Management Center, Air Dominance Division Contracting Office, Eglin Air Force Base, Florida, is the contracting activity (FA8675-20-C-0033).

(US DoD)

Kratos Awarded $3 Million+ to Upgrade Aussie Chinook Training Systems

December 26, 2019 Add Comment
26 Desmber 2019


Kratos Maintenance Blended Reconfigurable Aviation Trainers (MBRATs) (photo : Kratos)

Kratos Awarded $3 Million+ Contract for Aviation Trainer Enhancements by Australia Department of Defence

SAN DIEGO (GLOBE NEWSWIRE) -- Kratos Defense & Security Solutions, Inc. (Nasdaq: KTOS), a leading National Security Solutions provider, announced today that it was awarded a AUD $4,840,720.04 (approximately USD $3,300,000) contract by the Australia Department of Defence to deliver hardware, software and technical data package upgrades to their Kratos Maintenance Blended Reconfigurable Aviation Trainers (MBRATs) and CH-47F Chinook Avionics Trainer (CAT).

The CH-47F CAT is a High Fidelity Hands On Training System (HOTS) that provides full-task training through simulation of all avionics sub-systems and aircraft survivability equipment in an integrated configuration within a fully immersive physical environment. The CH-47F MBRAT blends a virtual immersive environment and spatial physical awareness with established CH-47F Chinook simulation software.

The enhanced MBRAT training capabilities enable the end user to increase student training throughput by enabling new training tasks to be performed on the upgraded MBRAT trainers and the CH-47F CAT simultaneously.


Kratos CH-47F Chinook Avionics Trainer (CAT) (photo : Kratos)

The CAT and MBRATs have enabled the Australian Department of Defence to establish a local CH-47F Chinook maintenance training center of excellence for the Australian military. Previously, maintenance training had been conducted in the United States, but with Kratos MBRATs and CAT the Australian Defence Force (ADF) is now self-sufficient in this regard.

“As the global demand for training continues to increase, Kratos is expanding its training footprint to support the demanding and complex training requirements of the U.S. and its allies worldwide by applying advanced technologies like those incorporated in the MBRAT and CAT,” said Jose Diaz, Senior Vice President of Kratos Training Solutions.

Kratos develops advanced, affordable training solutions for U.S. and allied forces that enhance learning retention and increase warfighter readiness. Kratos is driving innovation in military simulation and training programs by integrating the latest immersive technologies with its blended learning content and open architecture simulation systems for air, ground, maritime and soon space domains.

(Kratos)

Australia and NZ to Benefit from European Sat Nav Tech

December 24, 2019 Add Comment
25 Desember 2019


Australia and NZ are positioned to gain the benefits of major advances in Europe’s satellite navigation SBAS system EGNOS (image : Rockwell Collins)

Australia and NZ are positioned to gain the benefits of major advances in Europe’s satellite navigation SBAS (Satellite-based Augmentation System) system EGNOS following the announcement of a significant upgrade to be delivered by Thales Alenia Space.

The $127million upgrade will expand the EGNOS SBAS coverage zone, see the installation of a new generation of reference stations (RIMS), improved algorithms in the computation centre (CPF) to boost performance and enhanced system security.
Certification and commissioning of the new service is slated for 2023.

Thales Alenia Space VP Navigation Benoit Broudy said the company was committed to delivering the latest generation system to Australia should it be selected to deliver Australia & NZ’s SBAS (Satellite-based Augmentation System) for enhanced global positioning.

“The new version will bring significant benefits for regional aviation in Australia and NZ along with broader industry benefits across many sectors, from mining and resources to agriculture and transport," Broudy said.

The EGNOS system “Safety of Life” service enables aircraft to make precision approaches for landing without requiring ground-based landing aids.

In addition to providing the service in Europe, Thales Alenia Space is delivering the SBAS Korean Augmentation Satellite System (KASS) and SBAS for parts of Africa.

“Our record is one of long term investment in Australia’s advanced technology sector through technology transfer, collaboration with research agencies and Australian SMEs," Thales Australia CEO Chris Jenkins said. "We are excited about the opportunities to help build Australia’s space industry capability through world leading SBAS technology in line with the Statement of Strategic Intent signed with the Australian Space Agency.”

(ADM)

C-27J Fuselage Trainer for RAAF Arrived in Amberley

December 22, 2019 Add Comment
23 Desember 2019


C-27J Spartan fuselage trainer (photos : Down under Aviation News)

On 10 December 2019, a so-called C-27J Spartan Fuselage Trainer arrived at RAAF Base Amberley (QLD), following a journey by cargo ship from the USA to Brisbane (Australia). After arrival the aircraft moved to the Australian air base via road transport. The Spartan Fuselage Trainer is a training aid for 35 Squadron "Adept", simulating the cargo compartment and other fuselage systems as featured on a real Spartan. The fuselage can also be used to trial and develop new load-carrying methods and other practices on the Spartan.

The use of Fuselage Trainers and Cargo Compartment Trainers by the Royal Australian Air Force (RAAF) reduces the need for real aircraft to be used for this type of training, increasing the availability of aircraft for flying tasks. At RAAF Base Amberley, the C-27J Fuselage Trainer (FuT) is being installed within the dedicated 35 Squadron training facility, and is anticipated to be handed over for use by the squadron by mid-2020.



This particular FuT is reported to originally be a converted G222/C-27A fuselage. It was acquired by Australia from L3Harris Technologies. It will be installed and commissioned by L3Harris Link and L3Harris Oceania.

The previous identity of the airframe is yet unknown, but it might be one of five former USAF C-27As of which Scramble Magazine knows they are stored. Any info on the identity of the aircraft would be appreciated.

(Scramble)

Commonwealth Signs LAND 400 Phase 2 for 82 R400S-Mk2-D-HD RWS Contract

December 20, 2019 Add Comment
20 Desember 2019


R400S-Mk2-D-HD remote weapon system (photo : EOS)

The Department of Defence Capability Acquisition and Sustainment Group has executed a contract with EOS Defence Systems.

The contract valued at AUD$45M (GST exclusive) for the supply of Remote Weapon Systems (RWS) to the LAND 400 Phase 2 Combat Reconnaissance Vehicle project was previously announced on 24 August 2018. The contract signature on 16 December marks the commencement of the formal contract. EOS will provide extensive development, integration and testing activities on the Boxer Combat Reconnaissance Vehicle followed by the delivery of 82 R400S-MK2-D-HD remote weapon systems commencing in 2022.



The R400S-Mk2-D-HD remote weapon system is the latest high precision product from EOS Defence Systems and is capable of mounting a variety of weapons from small calibre machine guns through to lightweight cannons and anti-tank guided missiles. Combined with the current 230+ EOS remote weapon systems in-service with the Australian Army, this latest acquisition creates a fleet across multiple vehicles and delivers improvements in capability, operational effectiveness, training and cost of ownership.

Mr Grant Sanderson, CEO of EOS Defence Systems said: “EOS Defence Systems is very pleased to be able to support the ADF with this important capability. The R400 is world class Australian technology supported by over 70 Australian supply chain providers and is an excellent demonstration of Australian defence industry capability supporting Australia’s soldiers.”



All EOS systems for LAND 400 Phase 2 will be built in Australia in Queanbeyan, NSW and Hume, ACT and utilise components from its chain of 70+ Australian suppliers. Over 88% of EOS’ supply chain is sourced locally. In 2019 the company is set to contribute over AUD$64M to local suppliers, and this will grow significantly over the coming years.

(EOS)